Anderson Trail County Park in Granger: What's Built and What's Ahead

The site off Anderson Road looked like dirt and survey stakes for most of this year. By mid-October it has a poured pavilion pad with its trusses set, a framed gatehouse with a roof structure on top, and a restroom building framed and waiting for its roof. The two ponds already have fish in them.

Anderson Trail County Park is 115 acres of former corn and soybean ground. It is St. Joseph County Parks' first park in Granger, and according to WSBT, county officials had been trying to get a park like it built here for about 25 years. The work inside the park boundary is on track for a spring 2027 opening. The piece that is further behind sits outside it: a walking and biking connection from the surrounding neighborhoods to the front gate.

What the October update says is done

The best record of progress is the St. Joseph County Parks Board's own packet, not the news. Local TV and radio coverage stopped in April. The October 20, 2026 board packet carries an administrative update dated October 14 and signed by Executive Director Leslie Witkowski. Here is what it lists:

  • First construction package: Project B of Bid Package 1 is about 85% complete. Seeding and ongoing maintenance continue through the fall.
  • Pavilion: The concrete pad is poured and the trusses are installed.
  • Restroom building: It is framed. Fascia work is being prepared for roofing, and the sidewalks around it are going in.
  • Gatehouse: Framing is complete and the roof trusses are set.
  • Site systems: Light-pole foundations, more drainage work and the storm sewer are finished. The entrance is being dug out and prepared.
  • Electrical: Most of the underground conduit is in, with a little work left. Old utility pedestals and abandoned service lines have been removed or buried.
  • Finishes: The masonry contractor built a stone veneer mock-up panel for review.

That stone panel is a small detail, but it tells you the project has moved from ground work to what the buildings will look like. In April, then-executive director Steve Slauson told WSBT that crews would "soon move onto parts the community will notice from the road when driving by." The October report shows that phase well underway.

How a cornfield turned into a construction site

The timeline explains why the walls only went up this fall. Most of the money and time so far went into ground nobody will notice once the park opens.

  1. May 20, 2025. The county's final concept plan shows the entrance off Anderson Road.
  2. June 2025. The county council approves $4.9 million in funding for the park, WVPE reported. By then the parks department had owned the Anderson Road land for 22 years.
  3. October 2025. The board picks the name and officials break ground. A later WVPE report says the parks board awarded a $2.4 million contract for the major earthwork and paving in the fall.
  4. April 21, 2026. The board awards the second construction package to Brown & Brown General Contractors for $2,115,000. That covers the base bid plus four add-on items from the bid.
  5. April 29, 2026. WSBT reports that clearing, earthwork and compaction are done, the gravel base for roads and parking is down, both ponds are dug, and the trail markers are placed. Public opening is forecast for spring 2027.
  6. October 14, 2026. The board's update describes the buildings rising and the ponds stocked.

Slauson put a price on the delay. "Really, the cost is what's held us back for so long," he told WSBT, putting the total at $4.9 million to $5.9 million depending on the final components. The bond that pays for it also includes money to maintain a few other county parks.

In March, Parks Board President Larry Catanzarite told WVPE the board expected to finish the park by December. That was a construction finish date. The spring 2027 opening forecast came a month later and is still the public target. The October report doesn't give a new date in either direction.

What will be there on opening day

The October report lists amenities that are actually under construction. The 2025 concept plan has a longer wish list. The difference shows up mainly in recreation features, so the table splits them out.

Feature Where it stands as of October 2026
Two ponds, about three-quarters of an acre each Built and stocked
Pavilion Pad poured, trusses up
Restroom building Framed, being prepared for roofing
Gatehouse Framed, roof trusses set
One-mile paved trail, 10 feet wide Route marked in April
Half-mile dirt hiking loop into the woods Route marked in April
Two parking lots Gravel base in place as of April
Playground complex Named in April plans, not in October report
Sand volleyball, fishing pier On the 2025 concept plan, not confirmed in 2026 reports

According to WVPE's March report, the one item cut for budget reasons was a new maintenance building. Staff plan to use an existing building on the site instead. Slauson called the paved loop "one of the key features out here." For many visitors it will probably be the main draw: a mile of wide, flat pavement through a park.

The fish are in now. The catfish come in 2028.

Of everything in the October report, the ponds are the closest to finished. The board says both have been stocked with bluegill, redear sunfish and largemouth bass, using fish provided by the Indiana Department of Natural Resources. Channel catfish are scheduled for 2028.

The early stocking gives the bass and panfish two growing seasons before the catfish come in. Anyone planning to fish once the gates open will be casting into ponds that have had fish in them since this fall. Rules and fishing access haven't been announced yet.

The connection outside the fence

The county is building everything inside the park boundary. It isn't building a way for neighbors to walk or bike to the entrance.

That job belongs to Friends of Granger Paths, a volunteer group that funds trails through grants and donations. The group says it is working to fund a first phase that would run from the park entrance to the west entrance of the Terri Brooke neighborhood at Creekside Drive. Its Anderson Road Path page lays out three route options for that connection. The longer-term plan is a 2.5-mile path from Ash Road to Bittersweet Road.

The group's May 2, 2026 5K walk/run raised $8,820 for trail building in the community. That money supports the group's trail work generally; the group hasn't tied it to the Anderson path specifically.

The county project and the path project run on separate tracks with separate money. The park has a forecast opening season. The path is still at the funding stage.

Following along through the winter

The parks board publishes a packet before each monthly meeting in the St. Joseph County Parks Agenda Center. The administrative update near the front of each packet is where an opening date, roofing progress and any playground news will show up first. The Friends of Granger Paths site is where updates on the Creekside Drive connection would appear.

The park gets its name from the attorney Anderson Road was named for, a co-founder of the law firm May Oberfell Lorber, as WSBT reported when the board chose the name last October.

If you live near Anderson Road and want to talk through what a new county park nearby could mean for your street, Joey Atkins follows Granger projects like this one and is glad to go over the details with you. Work With Joey.